The customer's system landscape is expanded from a 2-system landscape to a 3-system landscape by means of a system copy. For this purpose, a HANA database is set up under Linux and then the new system is set up by a system copy.
Supplement
For the system setup, the preparations in the operating system are to be carried out first, as well as the subsequent installation of the SAP HANA 2.0 database. After preparing the operating system and installing the SAP HANA database, the SAP ERP 6.0 application server is installed using a system copy of the production system. After the system copy, the post-processing is carried out according to the system copy guide.
Subject description
By expanding to a 3 system landscape, the customer can better perform its tests. In addition, relevant updates are to be imported soon. It makes sense to have a 3 system landscape so that tests can be carried out better.